Tuesday, May 10, 2011

Update on Moseley Road baths – 10th May

Readers will be aware that Pool2 of Moseley Road baths has been closed since Christmas so that the lintel above the fire exit door in this pool can be repaired.

See previous posting at http://martinmullaney.blogspot.com/2011/04/update-on-moseley-road-baths-4-th-april.html

We were hoping that the work would be completed on or around 23rd May. Unfortunately, we are now looking at, at best, 13th June. Although this date may be pushed back due to additional problems in the basement of the baths.

At time of writing, the stainless steel lintel for the fire exit door in Pool 2 is being manufactured in Switzerland. We hope to have it at Moseley Road baths in 2 weeks time. Installing and removing the steel frame holding up the load bearing wall above the fire exit, will take a further three weeks – hence the 13th June date.

In addition, the Council’s structural engineers have raised concerns about the state of decade old acrow props underneath the former second class mens slipper baths. These acrow props hold the floor up, which in turn holds up the roof at this section of the building.

The acrow props are heavily rusted and need replacing immediately.

Our Structural engineers will only allow any replacement temporary acrow props to remain in situ for two months and want a permanent structure put in place. Estimated costed is £100,000.

The council’s Urban Design team are in the process of costing a temporary and permanent solution. They hope to have this information to me by the end of this week.

2 Comments:

At 1:26 PM, Blogger charlie said...

Martin, I live in Sutton Coldfield and am concerned about the lack of news on the removal of asbestos from the library. I note the detailed information you provide to your constituents and write to ask - are you obtaining this information as councillor or as chair of the relevant committee? The reason I ask this is that my councillors seems to be in the dark about the proposed work and, from what I can gather, have not attended any meetings with officials.

 
At 9:36 AM, Blogger grayblogs said...

In reply to > Update on Moseley Road baths – 10th May

You say the steel lintel is being manufactured in Switzerland !!

Why the heck Switzerland?

What's wrong with getting from Shefield or somewhere in Engaland?

 

Post a Comment